36-month execution architecture
A stage-gated route from readiness to legacy.
Nine coordinated Work Packages run in parallel, with formal evidence gates at M6, M12, M18, M30, M35 and M36 and a formal refinement/final-validation milestone at M22.
M1M6M12M18M24M30M36
WP1Living Labs & baselineUNISS · M1–12
WP2Feed readiness, processing, formulation & safetyAHIEVRAN · M1–18
WP3First Living-Lab implementationINAT · M8–18
WP4Adaptive refinement & final validationNRC · M19–28
WP5Animal health, product quality & acceptabilityTUM · M8–32
WP6Environmental, economic & social impactCNR · M3–33
WP7Business uptake, value chains, policy & scale-upAUA · M10–35
WP8Capacity, dissemination, exploitation & communicationSAFIR · M1–36
WP9Management, ethics & quality assuranceAUA · M1–36
G0 · M6Living-Lab readinessGovernance, baseline, roles, SOP/data framework and initial resource mapping.
G1 · M12Resource readinessNutrition, safety, regulatory eligibility, processing, formulation and essential QC.
G2 · M18First LL feasibilitySelect pathways for refinement based on performance, safety, cost and operator feasibility.
G3 · M30Technical / operational validationRelease ≥5 validated pathways (≥1/LL) for WP5–WP8 integration; operator-ready status is assigned only at G4; retain No-Go/boundary conditions.
G4 · M35Deployment readinessClassify ≥5 final pathways against Industrial Adoption Thresholds; target ≥3 operator-ready across ≥3 LLs, with remaining pathways trial-ready or No-Go as evidence dictates.
G5 · M36Final TRL & legacyFinal evidence chain, KPI/TRL closure, ownership, maintenance and uptake route.